Shagang implements April refurbishment

Shagang Group has released details of its refurbishment plans that have begun in April. These include work on a blast furnace, converter, electric arc furnace, and on plate and wire rod lines, Kallanish notes. Facility Halt period Daily output Accumulated lost output Blast furnace 16 days 1,500 tonnes 24,000t Converter 16d 5,000t  80,000t EAF 30d 3,000t 90,000t Wire rod 1…