Shagang implements April refurbishment
Shagang Group has released details of its refurbishment plans that have begun in April. These include work on a blast furnace, converter, electric arc furnace, and on plate and wire rod lines, Kallanish notes.
Facility
Halt period
Daily output
Accumulated lost output
Blast furnace
16 days
1,500 tonnes
24,000t
Converter
16d
5,000t
80,000t
EAF
30d
3,000t
90,000t
Wire rod
1…
This article contains premium data.
It is only available for active subscribers and clients currently
on trial. To continue reading, see the options below.
on trial. To continue reading, see the options below.
Truly global, user-friendly coverage of the steel and related markets and industry that delivers the essential information quickly while delivering on most occasions just the right amount of between-the-lines comment and interpretation for a near real time news service of this kind.
Anonymous
Very good overview of the weekly steel market.
Anonymous