Shagang arranges March refurbishment

Shagang Group has released details of its refurbishment plans that have begun this month. These include work on a converter, an electric arc furnace, and bar and wire rod production lines, Kallanish notes.  Facility Halt period Daily output Accumulated lost output Converter 21 days 5,000 tonnes 105,000 t EAF 31 days 3,000 t 93,000 t Bar line 31 days 2,000 t 62,000 t Wire rod…